News

West Cumberland hospital progress

It’s been a year since the first brick of the second phase on the £40m new hospital in Whitehaven was laid and a lot has happened in those 12 months.

In November 2022 the extension started to really take shape after months of work to prepare the ground and the whole site for this significant milestone. The first of the pre-cast concrete walls were delivered and erected on the site. Although lots of work had been going on behind the scenes to prepare the site for the arrival of the walls, this is the first time we saw what the finished build would look like.

This modern and cost effective method of construction allows for the walls to be made off site. Due to the significant weight of each panel it was necessary to transport them to site individually. The height of each panel meant that they had to be transported using a specialist trailer which supported the panels and allowed the transporting vehicle to pass safely under motorway bridges. The panels arrive complete with their windows fitted which include integral blinds.

To put the panels in place and effectively build the walls, three cranes were required. At first a large crawler crane (on tracks rather than wheels) was used in the buildings’ central courtyard area. This was then removed and a mobile crane was used to construct a smaller crane in the courtyard, the smaller crane and mobile crane were then used to complete the building.

Using pre-cast elements is time efficient and has allowed our appointed contractor GRAHAM to make great progress with the build.

The pre-cast concrete structure was completed in April 2023, allowing the construction team to push on inside the building. A total of 190 panels, which make up the walls, have been delivered and erected on site to complete the final build. The steel frames for the roof top plant rooms have been added this month with work ongoing to clad the plant room frames and waterproof the roof.

Electrical cable works, water and medical gas pipe work, to connect phase 2 with the existing hospital, has been ongoing during the night with the majority of the building services now ready for connection.

While working on the main building the GRAHAM team also progressed the new northern section of the ring road, this was opened on the 2nd May 2023 and it is now fully operational.

Thankfully the fire in the site cabins had a limited impact on the programme for the works, it was initially feared that operation may need to be halted for a time to allow welfare facilities to be reinstated. However, due to a quick response by GRAHAM, their supply chain and the Trust team, the site was up and running again in under a week.

Some key facts and figures around the build to date are:

·       Pre-cast concrete structure consists of – 190 Panels, 51 Columns, 519 Planks

·       Volume of concrete poured into foundations/slabs – 2019 m3

·       Length of drainage pipes laid – 1100 m

·       Linear metres of internal partitions – 800 m

·       Number of man hours worked – 1932 days

·       Volume of stone imported – 3,500 tonne

·       Volume of material exported – 20,124 tonne

·       Tonnage of steel for plant rooms on roof – 58 Tonne

Meanwhile plenty of refurbishment work has been taking place both inside and outside the hospital itself.

o   Roof refurbishment work has been completed on various parts of the older part of the building and well as external painting.

o   More staff office space has been made available across three levels. Furniture for these new office spaces is on order with staff expected to occupy them in early June.

o   Work is underway to install a new CT scanner and this areas is expected to be completed during the summer.

The new build extension will include a children’s and young people’s ward, a specialist palliative care ward, stepdown unit, care of the elderly ward and stroke rehabilitation unit.

We have made a lot of progress but there is still plenty to do. Phase two is expected to be fully complete with all service moved in and operational by summer 2024.

The services that will move into the phase 2 new build are explained below:

Copeland ward and Loweswater suite

The palliative care unit will be based on the ground floor of the hospital, which will mean patients can have access to a private outdoor courtyard area. Time spent away from the ward is extremely important to patients, a space where they can sit with family or friends and enjoy a quiet moment in the fresh air is imperative.

The Loweswater unit will benefit from a private entrance and will be separate from other wards and areas. This allows the patients, their families and carers the privacy and dignity they need under difficult circumstances. It will private rooms with more room for family and carers to stay with their loved ones in a much improved environment.

Paediatrics and maternity

The paediatric ward will move into the phase 2 new build and the maternity ward will re locate into their vacated space in phase 1.

The upgrade of the post-natal ward, will mean more en-suite, private rooms with more space, allowing for birth partners to stay with the pregnant people for longer periods of time.  It will also mean birth partners can stay during the induction process, something which the unit is unable to offer at this time.

Elderly care

The Care of the Elderly unit will move into the new build in 2024 and will deliver care for the elderly including those with dementia and those who are acutely frail.The new ward boasts six four-bedded bays, eight side rooms with dedicated en-suite facilities in each. There will also be a quiet room, for families and staff to use as well as a day room where patients can gather and interact with one another if they choose to.     The design of the ward has been a real collaboration between staff and the patients. The ward will be a dementia friendly space, with the colours and lay out carefully chosen with dementia patients in mind.

The staff on the ward will also benefit from a new staff room and office space and dedicated storage space, something which is lacking on the current ward.  

Stroke

The Stroke rehabilitation unit will be located on the ground floor in order to give access to the private courtyard which will become an extended rehabilitation area. This will be hugely beneficial to preparing patients to return to their lives outside of the hospital; having an outdoor space to build their strength and gain confidence away from the safety net of the ward is very important.

The design of the new stroke unit was a collaborative project between the stroke team alongside input from patients and their families. One of the main issues raised was space. There is a lot of specialist equipment used in the unit, so adequate space was vital to fully utilise this equipment and give patients the space they need to safely move around the ward.

There will be a private family room away from the ward itself so staff can meet with the families and carers to discuss treatment and discharge plans.

There is a mixture of single rooms and bays as well. Some of our patients may be with us for a longer stay and are keen to have interaction with other patients and others will want the privacy of a single room.

The new unit will have a dedicated space for staff to meet and have confidential discussions.”

Categories
NewsTECHNOLOGY

Join our audience of healthcare industry professionals

X